Kesoram Industries Ltd. had informed the Exchange that the normal output in the Raw Mill of Unit III of the Vasavadatta Section of the Company was expected to start by the end of September,2007. In this connection, the Company has now informed the Exchange that: "The new roller from our supplier Polysius AG.Germany, expected to arrive at factory site by early September, 2007 by sea route, was airlifted by a chartered flight of 'Antonove124-100 aircraft and the same reached the site by second week of August,07 itself. On fitting of the same in the said Raw Mill the normal production has started. Further, the temporary measure of earlier converting the Cement Mill into Raw Mill has also been reversed to the original position and the normal Cement production has started by the said Unit III. Thus, the extra efforts put by the management have resulted in the starting of the normal regular production in the said unit one month ahead of the original estimation".